Timeline with dependencies

Last modified: 2026-11-02 12:19by Erik Hagen ID: b5b5edfa-2185-4b4a-925b-1ef9e8c14868 SAMT-X/solution-task-management

The Timeline view in GitHub Projects shows tasks along a time axis, but does not draw which tasks wait for each other. The charts on this page do. They are generated automatically from the boards every hour, and updated on docs shortly after. A fixed script makes them following the rules on this page. If a run fails, the previous chart stays until the error is fixed, and the date below the chart shows when it was made. See Scheduled runs.

Click a title, a bar or an arrow to see the task in a window on top of the chart. Move the window by its title bar and resize it from the bottom right corner. Links to other tasks inside the window open in the same window. Click somewhere outside the window that is not a link, press Esc or click × to close it. Ctrl-click opens the task on GitHub instead. Hover to see status, dates and dependencies. The chart is shown at full size in a frame that can be scrolled sideways and up and down. The toolbar above the chart zooms out and in (− and +), back to full size (100 %) or so that the whole width fits (Fit width). Ctrl + mouse wheel over the chart zooms only the chart. The chart can also be dragged with the mouse (hand cursor) in any direction. A click without dragging opens the task as before. «Open the chart in a new window» shows the chart on its own, where it can be saved or copied.

The line Show below the toolbar chooses which tasks are shown: All, Active (open), Delayed (late start, due date passed or forecast after the due date), Completed or Cancelled (closed without being done). A parent is shown when it or one of its sub-issues matches, so the context does not disappear. If you are logged in on docs, there is also the button My tasks. It highlights with a yellow background the tasks where you are Responsible or assignee, whatever selection is shown. The choices only last until the page is reloaded.

The window fetches the task from GitHub. Without logging in, GitHub allows about 60 lookups an hour. If the limit is reached, a link to GitHub is shown instead, and logging in raises the limit.

First version, for trial (solution-task-management#32). Task titles are in the language they were written in, usually Norwegian.

Examples

The examples below show typical situations, with a few tasks each. The legend below each chart shows only what is in that chart. The examples are on the board «[EXAMPLE] Timeline». They are not tasks, and they live in a repository of their own, solution-task-management-examples. Each situation has its own label, and an example can be part of several. The dates are moved automatically every week, so the examples always sit around today’s date. The examples therefore show Start date and Due date as what has happened, not the history. See Examples in the documentation.

A simple plan

A is completed (✓). L is in progress: the dark part is what has been done until today, and the light part is the rest of the plan until the due date. M has not started and waits for L (⛔). The arrow goes from L to M, and the ring on the arrow shows that the dependency is described in M.

100 % Open the chart in a new window ↗
3031Nov 2026123456789101112131415161718192021222324252627282930Dec 20261solution-task-management-examples#1 Eksempel A: Kartlegge behov Done (closed: completed) Start: Nov 2 (started (In progress)) End: Nov 6 (finished)✓ Eksempel A: Kartlegge behov#1solution-task-management-examples#1 Eksempel A: Kartlegge behov Done (closed: completed) Start: Nov 2 (started (In progress)) End: Nov 6 (finished)solution-task-management-examples#15 Eksempel L: Intervjue fagfolk In progress Start: Nov 13 (started (In progress)) End: Nov 20 (Due date) Blocking: solution-task-management-examples#16Eksempel L: Intervjue fagfolk#15solution-task-management-examples#15 Eksempel L: Intervjue fagfolk In progress Start: Nov 13 (started (In progress)) End: Nov 20 (Due date) Blocking: solution-task-management-examples#16solution-task-management-examples#16 Eksempel M: Planlegge workshop To do Start: Nov 23 (Start date) End: Nov 27 (Due date) Blocked by: solution-task-management-examples#15⛔ Eksempel M: Planlegge workshop#16solution-task-management-examples#16 Eksempel M: Planlegge workshop To do Start: Nov 23 (Start date) End: Nov 27 (Due date) Blocked by: solution-task-management-examples#15solution-task-management-examples#16 Eksempel M: Planlegge workshop waits for solution-task-management-examples#15 Eksempel L: Intervjue fagfolk Why: workshopen bygger på det som kom fram i intervjuene No slack (#15 ends Nov 20, #16 starts Nov 23) Linked Nov 2 by erikhag1git Click to open #16TodayArrow: waits forRing: the dependency is described⛔Waits for an open taskDark: has happenedLight: dates set✓CompletedGenerated 2026-11-15 from[EXAMPLE] Timeline.

Dependencies and slack

M, N and O all wait for L. Hover over an arrow to see the slack. M starts the working day after L ends, with no slack. N has a week of slack, but the dependency is not described, so the arrow has no ring. O is due to start before L is finished. The arrow is red because the plan does not add up, and the forecast (light red) shows when O can be finished if it starts after L.

100 % Open the chart in a new window ↗
Nov 2026101112131415161718192021222324252627282930Dec 202612345678solution-task-management-examples#15 Eksempel L: Intervjue fagfolk In progress Start: Nov 13 (started (In progress)) End: Nov 20 (Due date) Blocking: solution-task-management-examples#18, solution-task-management-examples#16, solution-task-management-examples#17Eksempel L: Intervjue fagfolk#15solution-task-management-examples#15 Eksempel L: Intervjue fagfolk In progress Start: Nov 13 (started (In progress)) End: Nov 20 (Due date) Blocking: solution-task-management-examples#18, solution-task-management-examples#16, solution-task-management-examples#17solution-task-management-examples#18 Eksempel O: Lage presentasjon To do Start: Nov 19 (Start date) End: Nov 25 (Due date) Forecast: finished Nov 27, 2 working days after the due date Nov 25 Blocked by: solution-task-management-examples#15⛔ Eksempel O: Lage presentasjon#18solution-task-management-examples#18 Eksempel O: Lage presentasjon To do Start: Nov 19 (Start date) End: Nov 25 (Due date) Forecast: finished Nov 27, 2 working days after the due date Nov 25 Blocked by: solution-task-management-examples#15solution-task-management-examples#16 Eksempel M: Planlegge workshop To do Start: Nov 23 (Start date) End: Nov 27 (Due date) Blocked by: solution-task-management-examples#15⛔ Eksempel M: Planlegge workshop#16solution-task-management-examples#16 Eksempel M: Planlegge workshop To do Start: Nov 23 (Start date) End: Nov 27 (Due date) Blocked by: solution-task-management-examples#15solution-task-management-examples#17 Eksempel N: Oppsummere intervjuene To do Start: Nov 30 (Start date) End: Dec 4 (Due date) Blocked by: solution-task-management-examples#15⛔ Eksempel N: Oppsummere intervjuene#17solution-task-management-examples#17 Eksempel N: Oppsummere intervjuene To do Start: Nov 30 (Start date) End: Dec 4 (Due date) Blocked by: solution-task-management-examples#15solution-task-management-examples#18 Eksempel O: Lage presentasjon waits for solution-task-management-examples#15 Eksempel L: Intervjue fagfolk Why: presentasjonen skal vise funnene fra intervjuene Overlap: 2 working days (#15 ends Nov 20, #18 starts Nov 19) Linked Nov 2 by erikhag1git Click to open #18solution-task-management-examples#16 Eksempel M: Planlegge workshop waits for solution-task-management-examples#15 Eksempel L: Intervjue fagfolk Why: workshopen bygger på det som kom fram i intervjuene No slack (#15 ends Nov 20, #16 starts Nov 23) Linked Nov 2 by erikhag1git Click to open #16solution-task-management-examples#17 Eksempel N: Oppsummere intervjuene waits for solution-task-management-examples#15 Eksempel L: Intervjue fagfolk Not described. Write a line under the heading Avhengigheter (Dependencies) in #17. Slack: 5 working days (#15 ends Nov 20, #17 starts Nov 30) Linked Nov 2 by erikhag1git Click to open #17TodayArrow: waits forRed arrow: blocking task ends too lateRing: the dependency is described⛔Waits for an open taskDark: has happenedLight: dates setRed: after the due date (light: forecast)Generated 2026-11-15 from[EXAMPLE] Timeline.

A delay that propagates

B should have been finished Friday last week, and is red from the due date. D should have started the same Friday (yellow border and line), but is still waiting for B and C. When C is finished, D cannot make its due date. E waits for D, and is therefore late too, even though the due date of E has not been reached.

100 % Open the chart in a new window ↗
Nov 2026681012141618202224262830Dec 2026246810121416182022242628solution-task-management-examples#2 Eksempel B: Skissere løsning In progress Start: Nov 9 (started (In progress)) End: Nov 13 (Due date) Overdue: should have been finished Nov 13 Blocked by: solution-task-management-examples#1 (not in the chart) Blocking: solution-task-management-examples#4Eksempel B: Skissere løsning#2solution-task-management-examples#2 Eksempel B: Skissere løsning In progress Start: Nov 9 (started (In progress)) End: Nov 13 (Due date) Overdue: should have been finished Nov 13 Blocked by: solution-task-management-examples#1 (not in the chart) Blocking: solution-task-management-examples#4solution-task-management-examples#3 Eksempel C: Avklare juridiske spørsmål In progress Start: Nov 11 (started (In progress)) End: Nov 25 (Due date) Blocked by: solution-task-management-examples#1 (not in the chart) Blocking: solution-task-management-examples#4Eksempel C: Avklare juridiske spørsmål#3solution-task-management-examples#3 Eksempel C: Avklare juridiske spørsmål In progress Start: Nov 11 (started (In progress)) End: Nov 25 (Due date) Blocked by: solution-task-management-examples#1 (not in the chart) Blocking: solution-task-management-examples#4solution-task-management-examples#4 Eksempel D: Bygge prototype Ready Start: Nov 13 (Start date) End: Dec 4 (Due date) Late start: should have started Nov 13 Forecast: finished Dec 17, 9 working days after the due date Dec 4 Blocked by: solution-task-management-examples#3, solution-task-management-examples#2 Blocking: solution-task-management-examples#5⛔ Eksempel D: Bygge prototype#4solution-task-management-examples#4 Eksempel D: Bygge prototype Ready Start: Nov 13 (Start date) End: Dec 4 (Due date) Late start: should have started Nov 13 Forecast: finished Dec 17, 9 working days after the due date Dec 4 Blocked by: solution-task-management-examples#3, solution-task-management-examples#2 Blocking: solution-task-management-examples#5solution-task-management-examples#5 Eksempel E: Teste med brukere To do Start: Dec 7 (Start date) End: Dec 11 (Due date) Forecast: finished Dec 24, 9 working days after the due date Dec 11 Blocked by: solution-task-management-examples#4⛔ Eksempel E: Teste med brukere#5solution-task-management-examples#5 Eksempel E: Teste med brukere To do Start: Dec 7 (Start date) End: Dec 11 (Due date) Forecast: finished Dec 24, 9 working days after the due date Dec 11 Blocked by: solution-task-management-examples#4solution-task-management-examples#4 Eksempel D: Bygge prototype waits for solution-task-management-examples#3 Eksempel C: Avklare juridiske spørsmål Why: prototypen kan ikke behandle personopplysninger før behandlingsgrunnlaget er avklart Overlap: 9 working days (#3 ends Nov 25, #4 starts Nov 13) Linked Nov 1 by erikhag1git Click to open #4solution-task-management-examples#4 Eksempel D: Bygge prototype waits for solution-task-management-examples#2 Eksempel B: Skissere løsning Why: prototypen bygger på løsningsskissen Overlap: 1 working days (#2 ends Nov 15, #4 starts Nov 13) Linked Nov 1 by erikhag1git Click to open #4solution-task-management-examples#5 Eksempel E: Teste med brukere waits for solution-task-management-examples#4 Eksempel D: Bygge prototype Why: brukertesten trenger en prototype som virker Overlap: 9 working days (#4 ends Dec 17, #5 starts Dec 7) Linked Nov 1 by erikhag1git Click to open #5TodayRed arrow: blocking task ends too lateRing: the dependency is described⛔Waits for an open taskDark: has happenedLight: dates setYellow border and line: late startRed: after the due date (light: forecast)Generated 2026-11-15 from[EXAMPLE] Timeline.

Without dates

F and G have neither Start date nor Due date, so they are placed after the tasks they wait for: G after B and F after E. The bars are dashed because the dates are calculated. G has Duration 3. F has no duration and is assumed to take one week, as stated below the chart. B is delayed, and so G is moved as well.

100 % Open the chart in a new window ↗
Nov 2026681012141618202224262830Dec 2026246810121416182022solution-task-management-examples#2 Eksempel B: Skissere løsning In progress Start: Nov 9 (started (In progress)) End: Nov 13 (Due date) Overdue: should have been finished Nov 13 Blocked by: solution-task-management-examples#1 (not in the chart) Blocking: solution-task-management-examples#7Eksempel B: Skissere løsning#2solution-task-management-examples#2 Eksempel B: Skissere løsning In progress Start: Nov 9 (started (In progress)) End: Nov 13 (Due date) Overdue: should have been finished Nov 13 Blocked by: solution-task-management-examples#1 (not in the chart) Blocking: solution-task-management-examples#7solution-task-management-examples#7 Eksempel G: Dokumentere erfaringer To do Start: Nov 16 (after the tasks it waits for) End: Nov 18 (calculated from start and duration) Duration: 3 working days Blocked by: solution-task-management-examples#2⛔ Eksempel G: Dokumentere erfaringer#7solution-task-management-examples#7 Eksempel G: Dokumentere erfaringer To do Start: Nov 16 (after the tasks it waits for) End: Nov 18 (calculated from start and duration) Duration: 3 working days Blocked by: solution-task-management-examples#2solution-task-management-examples#5 Eksempel E: Teste med brukere To do Start: Dec 7 (Start date) End: Dec 11 (Due date) Blocked by: solution-task-management-examples#4 (not in the chart) Blocking: solution-task-management-examples#6⛔ Eksempel E: Teste med brukere#5solution-task-management-examples#5 Eksempel E: Teste med brukere To do Start: Dec 7 (Start date) End: Dec 11 (Due date) Blocked by: solution-task-management-examples#4 (not in the chart) Blocking: solution-task-management-examples#6solution-task-management-examples#6 Eksempel F: Beslutte videreføring To do Start: Dec 14 (after the tasks it waits for) End: Dec 18 (calculated from start and duration) Duration: not set, assumed 5 working days Blocked by: solution-task-management-examples#5⛔ Eksempel F: Beslutte videreføring#6solution-task-management-examples#6 Eksempel F: Beslutte videreføring To do Start: Dec 14 (after the tasks it waits for) End: Dec 18 (calculated from start and duration) Duration: not set, assumed 5 working days Blocked by: solution-task-management-examples#5solution-task-management-examples#7 Eksempel G: Dokumentere erfaringer waits for solution-task-management-examples#2 Eksempel B: Skissere løsning Not described. Write a line under the heading Avhengigheter (Dependencies) in #7. No slack (#2 ends Nov 15, #7 starts Nov 16) Linked Nov 1 by erikhag1git Click to open #7solution-task-management-examples#6 Eksempel F: Beslutte videreføring waits for solution-task-management-examples#5 Eksempel E: Teste med brukere Why: beslutningen bygger på resultatene fra brukertesten No slack (#5 ends Dec 11, #6 starts Dec 14) Linked Nov 1 by erikhag1git Click to open #6TodayArrow: waits forRing: the dependency is described⛔Waits for an open taskDark: has happenedLight: dates setDashed: calculated or assumedRed: after the due date (light: forecast)Generated 2026-11-15 from[EXAMPLE] Timeline. One task has no Duration and is assumed to take one week.

Due date and duration, but no start date

When the start date is missing, it is calculated backwards from the due date with the duration (dashed bar). I has no dependencies, but the calculated start date has passed (yellow), and today plus the duration goes past the due date, so the forecast is red. H waits for C. To make its due date, H would have to start before C is finished, so the arrow is red, and the earliest start after C plus the duration goes past the due date.

100 % Open the chart in a new window ↗
Nov 202689101112131415161718192021222324252627282930Dec 2026123456solution-task-management-examples#9 Eksempel I: Bestille testmiljø To do Start: Nov 11 (calculated from end and duration) End: Nov 20 (Due date) Duration: 8 working days Late start: should have started Nov 11 Forecast: finished Nov 25, 3 working days after the due date Nov 20Eksempel I: Bestille testmiljø#9solution-task-management-examples#9 Eksempel I: Bestille testmiljø To do Start: Nov 11 (calculated from end and duration) End: Nov 20 (Due date) Duration: 8 working days Late start: should have started Nov 11 Forecast: finished Nov 25, 3 working days after the due date Nov 20solution-task-management-examples#3 Eksempel C: Avklare juridiske spørsmål In progress Start: Nov 11 (started (In progress)) End: Nov 25 (Due date) Blocked by: solution-task-management-examples#1 (not in the chart) Blocking: solution-task-management-examples#8Eksempel C: Avklare juridiske spørsmål#3solution-task-management-examples#3 Eksempel C: Avklare juridiske spørsmål In progress Start: Nov 11 (started (In progress)) End: Nov 25 (Due date) Blocked by: solution-task-management-examples#1 (not in the chart) Blocking: solution-task-management-examples#8solution-task-management-examples#8 Eksempel H: Vurdere personvernkonsekvenser To do Start: Nov 24 (calculated from end and duration) End: Nov 30 (Due date) Duration: 5 working days Forecast: finished Dec 2, 2 working days after the due date Nov 30 Blocked by: solution-task-management-examples#3⛔ Eksempel H: Vurdere personvernkonsekvenser#8solution-task-management-examples#8 Eksempel H: Vurdere personvernkonsekvenser To do Start: Nov 24 (calculated from end and duration) End: Nov 30 (Due date) Duration: 5 working days Forecast: finished Dec 2, 2 working days after the due date Nov 30 Blocked by: solution-task-management-examples#3solution-task-management-examples#8 Eksempel H: Vurdere personvernkonsekvenser waits for solution-task-management-examples#3 Eksempel C: Avklare juridiske spørsmål Why: vurderingen bygger på de juridiske avklaringene Overlap: 2 working days (#3 ends Nov 25, #8 starts Nov 24) Linked Nov 1 by erikhag1git Click to open #8TodayRed arrow: blocking task ends too lateRing: the dependency is described⛔Waits for an open taskDark: has happenedLight: dates setDashed: calculated or assumedYellow border and line: late startRed: after the due date (light: forecast)Generated 2026-11-15 from[EXAMPLE] Timeline.

Closed: completed and cancelled

A is completed (✓). J was closed without being done (✕, hatched bar), in GitHub with «Close as not planned». Both are grey with the title struck through.

Sub-issues

K has three sub-issues: K1 is completed, K2 has not started and is past its due date, and K3 is in progress but waits for K2. K shows the progress 1/3, and the bracket has a red border because K2 is delayed. The gap in the dark part is the days between K1 and K3 when neither was being worked on. Click ▾ in front of K to collapse the sub-issues, and ▸ to expand them again. K3 has Responsible set, so it gets a yellow background with My tasks for the person with that user name.

100 % Open the chart in a new window ↗
Nov 202634567891011121314151617181920212223242526272829Collapse or expand the sub-issues▾solution-task-management-examples#11 Eksempel K: Gjennomføre brukertester In progress Start: Nov 6 (from the sub-issues) End: Nov 25 (from the sub-issues) Sub-issues: 1 of 3 completed At least one sub-issue is delayedEksempel K: Gjennomføre brukertester#11 · 1/3solution-task-management-examples#11 Eksempel K: Gjennomføre brukertester In progress Start: Nov 6 (from the sub-issues) End: Nov 25 (from the sub-issues) Sub-issues: 1 of 3 completed At least one sub-issue is delayedsolution-task-management-examples#12 Eksempel K1: Rekruttere testpersoner Done (closed: completed) Start: Nov 6 (started (In progress)) End: Nov 10 (finished)✓ Eksempel K1: Rekruttere testpersoner#12solution-task-management-examples#12 Eksempel K1: Rekruttere testpersoner Done (closed: completed) Start: Nov 6 (started (In progress)) End: Nov 10 (finished)solution-task-management-examples#13 Eksempel K2: Lage testmanus To do Start: Nov 10 (Start date) End: Nov 15 (Due date) Duration: 4 working days Late start: should have started Nov 10 Forecast: finished Nov 19, 4 working days after the due date Nov 15 Blocking: solution-task-management-examples#14Eksempel K2: Lage testmanus#13solution-task-management-examples#13 Eksempel K2: Lage testmanus To do Start: Nov 10 (Start date) End: Nov 15 (Due date) Duration: 4 working days Late start: should have started Nov 10 Forecast: finished Nov 19, 4 working days after the due date Nov 15 Blocking: solution-task-management-examples#14solution-task-management-examples#14 Eksempel K3: Gjennomføre testene In progress Start: Nov 15 (started (In progress)) End: Nov 25 (Due date) Blocked by: solution-task-management-examples#13⛔ Eksempel K3: Gjennomføre testene#14solution-task-management-examples#14 Eksempel K3: Gjennomføre testene In progress Start: Nov 15 (started (In progress)) End: Nov 25 (Due date) Blocked by: solution-task-management-examples#13solution-task-management-examples#14 Eksempel K3: Gjennomføre testene waits for solution-task-management-examples#13 Eksempel K2: Lage testmanus Why: testene trenger manuset Overlap: 4 working days (#13 ends Nov 19, #14 starts Nov 15) Linked Nov 2 by erikhag1git Click to open #14TodayRed arrow: blocking task ends too lateRing: the dependency is described⛔Waits for an open taskDark: has happenedLight: dates setYellow border and line: late startRed: after the due date (light: forecast)✓CompletedBracket: the sub-issues together (red border: one is delayed)▾ ▸Collapse and expand the sub-issuesYellow: My tasks (signed in)Generated 2026-11-15 from[EXAMPLE] Timeline.

All the examples together

This is the board with all the examples in one chart. Try the filter above the chart, for example Delayed.

100 % Open the chart in a new window ↗
30Nov 20261357911131517192123252729Dec 2026135791113151719212325272931Jan 202724solution-task-management-examples#1 Eksempel A: Kartlegge behov Done (closed: completed) Start: Nov 2 (started (In progress)) End: Nov 6 (finished) Blocking: solution-task-management-examples#10, solution-task-management-examples#2, solution-task-management-examples#3✓ Eksempel A: Kartlegge behov#1solution-task-management-examples#1 Eksempel A: Kartlegge behov Done (closed: completed) Start: Nov 2 (started (In progress)) End: Nov 6 (finished) Blocking: solution-task-management-examples#10, solution-task-management-examples#2, solution-task-management-examples#3Collapse or expand the sub-issues▾solution-task-management-examples#11 Eksempel K: Gjennomføre brukertester In progress Start: Nov 6 (from the sub-issues) End: Nov 25 (from the sub-issues) Sub-issues: 1 of 3 completed At least one sub-issue is delayedEksempel K: Gjennomføre brukertester#11 · 1/3solution-task-management-examples#11 Eksempel K: Gjennomføre brukertester In progress Start: Nov 6 (from the sub-issues) End: Nov 25 (from the sub-issues) Sub-issues: 1 of 3 completed At least one sub-issue is delayedsolution-task-management-examples#12 Eksempel K1: Rekruttere testpersoner Done (closed: completed) Start: Nov 6 (started (In progress)) End: Nov 10 (finished)✓ Eksempel K1: Rekruttere testpersoner#12solution-task-management-examples#12 Eksempel K1: Rekruttere testpersoner Done (closed: completed) Start: Nov 6 (started (In progress)) End: Nov 10 (finished)solution-task-management-examples#13 Eksempel K2: Lage testmanus To do Start: Nov 10 (Start date) End: Nov 15 (Due date) Duration: 4 working days Late start: should have started Nov 10 Forecast: finished Nov 19, 4 working days after the due date Nov 15 Blocking: solution-task-management-examples#14Eksempel K2: Lage testmanus#13solution-task-management-examples#13 Eksempel K2: Lage testmanus To do Start: Nov 10 (Start date) End: Nov 15 (Due date) Duration: 4 working days Late start: should have started Nov 10 Forecast: finished Nov 19, 4 working days after the due date Nov 15 Blocking: solution-task-management-examples#14solution-task-management-examples#14 Eksempel K3: Gjennomføre testene In progress Start: Nov 15 (started (In progress)) End: Nov 25 (Due date) Blocked by: solution-task-management-examples#13⛔ Eksempel K3: Gjennomføre testene#14solution-task-management-examples#14 Eksempel K3: Gjennomføre testene In progress Start: Nov 15 (started (In progress)) End: Nov 25 (Due date) Blocked by: solution-task-management-examples#13solution-task-management-examples#10 Eksempel J: Pilotere i to kommuner Done (closed: not planned) Start: Nov 9 (started (In progress)) End: Nov 12 (finished) Blocked by: solution-task-management-examples#1✕ Eksempel J: Pilotere i to kommuner#10solution-task-management-examples#10 Eksempel J: Pilotere i to kommuner Done (closed: not planned) Start: Nov 9 (started (In progress)) End: Nov 12 (finished) Blocked by: solution-task-management-examples#1solution-task-management-examples#2 Eksempel B: Skissere løsning In progress Start: Nov 9 (started (In progress)) End: Nov 13 (Due date) Overdue: should have been finished Nov 13 Blocked by: solution-task-management-examples#1 Blocking: solution-task-management-examples#4, solution-task-management-examples#7Eksempel B: Skissere løsning#2solution-task-management-examples#2 Eksempel B: Skissere løsning In progress Start: Nov 9 (started (In progress)) End: Nov 13 (Due date) Overdue: should have been finished Nov 13 Blocked by: solution-task-management-examples#1 Blocking: solution-task-management-examples#4, solution-task-management-examples#7solution-task-management-examples#9 Eksempel I: Bestille testmiljø To do Start: Nov 11 (calculated from end and duration) End: Nov 20 (Due date) Duration: 8 working days Late start: should have started Nov 11 Forecast: finished Nov 25, 3 working days after the due date Nov 20Eksempel I: Bestille testmiljø#9solution-task-management-examples#9 Eksempel I: Bestille testmiljø To do Start: Nov 11 (calculated from end and duration) End: Nov 20 (Due date) Duration: 8 working days Late start: should have started Nov 11 Forecast: finished Nov 25, 3 working days after the due date Nov 20solution-task-management-examples#3 Eksempel C: Avklare juridiske spørsmål In progress Start: Nov 11 (started (In progress)) End: Nov 25 (Due date) Blocked by: solution-task-management-examples#1 Blocking: solution-task-management-examples#4, solution-task-management-examples#8Eksempel C: Avklare juridiske spørsmål#3solution-task-management-examples#3 Eksempel C: Avklare juridiske spørsmål In progress Start: Nov 11 (started (In progress)) End: Nov 25 (Due date) Blocked by: solution-task-management-examples#1 Blocking: solution-task-management-examples#4, solution-task-management-examples#8solution-task-management-examples#15 Eksempel L: Intervjue fagfolk In progress Start: Nov 13 (started (In progress)) End: Nov 20 (Due date) Blocking: solution-task-management-examples#18, solution-task-management-examples#16, solution-task-management-examples#17Eksempel L: Intervjue fagfolk#15solution-task-management-examples#15 Eksempel L: Intervjue fagfolk In progress Start: Nov 13 (started (In progress)) End: Nov 20 (Due date) Blocking: solution-task-management-examples#18, solution-task-management-examples#16, solution-task-management-examples#17solution-task-management-examples#4 Eksempel D: Bygge prototype Ready Start: Nov 13 (Start date) End: Dec 4 (Due date) Late start: should have started Nov 13 Forecast: finished Dec 17, 9 working days after the due date Dec 4 Blocked by: solution-task-management-examples#3, solution-task-management-examples#2 Blocking: solution-task-management-examples#5⛔ Eksempel D: Bygge prototype#4solution-task-management-examples#4 Eksempel D: Bygge prototype Ready Start: Nov 13 (Start date) End: Dec 4 (Due date) Late start: should have started Nov 13 Forecast: finished Dec 17, 9 working days after the due date Dec 4 Blocked by: solution-task-management-examples#3, solution-task-management-examples#2 Blocking: solution-task-management-examples#5solution-task-management-examples#7 Eksempel G: Dokumentere erfaringer To do Start: Nov 16 (after the tasks it waits for) End: Nov 18 (calculated from start and duration) Duration: 3 working days Blocked by: solution-task-management-examples#2⛔ Eksempel G: Dokumentere erfaringer#7solution-task-management-examples#7 Eksempel G: Dokumentere erfaringer To do Start: Nov 16 (after the tasks it waits for) End: Nov 18 (calculated from start and duration) Duration: 3 working days Blocked by: solution-task-management-examples#2solution-task-management-examples#18 Eksempel O: Lage presentasjon To do Start: Nov 19 (Start date) End: Nov 25 (Due date) Forecast: finished Nov 27, 2 working days after the due date Nov 25 Blocked by: solution-task-management-examples#15⛔ Eksempel O: Lage presentasjon#18solution-task-management-examples#18 Eksempel O: Lage presentasjon To do Start: Nov 19 (Start date) End: Nov 25 (Due date) Forecast: finished Nov 27, 2 working days after the due date Nov 25 Blocked by: solution-task-management-examples#15solution-task-management-examples#16 Eksempel M: Planlegge workshop To do Start: Nov 23 (Start date) End: Nov 27 (Due date) Blocked by: solution-task-management-examples#15⛔ Eksempel M: Planlegge workshop#16solution-task-management-examples#16 Eksempel M: Planlegge workshop To do Start: Nov 23 (Start date) End: Nov 27 (Due date) Blocked by: solution-task-management-examples#15solution-task-management-examples#8 Eksempel H: Vurdere personvernkonsekvenser To do Start: Nov 24 (calculated from end and duration) End: Nov 30 (Due date) Duration: 5 working days Forecast: finished Dec 2, 2 working days after the due date Nov 30 Blocked by: solution-task-management-examples#3⛔ Eksempel H: Vurdere personvernkonsekvenser#8solution-task-management-examples#8 Eksempel H: Vurdere personvernkonsekvenser To do Start: Nov 24 (calculated from end and duration) End: Nov 30 (Due date) Duration: 5 working days Forecast: finished Dec 2, 2 working days after the due date Nov 30 Blocked by: solution-task-management-examples#3solution-task-management-examples#17 Eksempel N: Oppsummere intervjuene To do Start: Nov 30 (Start date) End: Dec 4 (Due date) Blocked by: solution-task-management-examples#15⛔ Eksempel N: Oppsummere intervjuene#17solution-task-management-examples#17 Eksempel N: Oppsummere intervjuene To do Start: Nov 30 (Start date) End: Dec 4 (Due date) Blocked by: solution-task-management-examples#15solution-task-management-examples#5 Eksempel E: Teste med brukere To do Start: Dec 7 (Start date) End: Dec 11 (Due date) Forecast: finished Dec 24, 9 working days after the due date Dec 11 Blocked by: solution-task-management-examples#4 Blocking: solution-task-management-examples#6⛔ Eksempel E: Teste med brukere#5solution-task-management-examples#5 Eksempel E: Teste med brukere To do Start: Dec 7 (Start date) End: Dec 11 (Due date) Forecast: finished Dec 24, 9 working days after the due date Dec 11 Blocked by: solution-task-management-examples#4 Blocking: solution-task-management-examples#6solution-task-management-examples#6 Eksempel F: Beslutte videreføring To do Start: Dec 25 (after the tasks it waits for) End: Dec 31 (calculated from start and duration) Duration: not set, assumed 5 working days Blocked by: solution-task-management-examples#5⛔ Eksempel F: Beslutte videreføring#6solution-task-management-examples#6 Eksempel F: Beslutte videreføring To do Start: Dec 25 (after the tasks it waits for) End: Dec 31 (calculated from start and duration) Duration: not set, assumed 5 working days Blocked by: solution-task-management-examples#5solution-task-management-examples#14 Eksempel K3: Gjennomføre testene waits for solution-task-management-examples#13 Eksempel K2: Lage testmanus Why: testene trenger manuset Overlap: 4 working days (#13 ends Nov 19, #14 starts Nov 15) Linked Nov 2 by erikhag1git Click to open #14solution-task-management-examples#10 Eksempel J: Pilotere i to kommuner waits for solution-task-management-examples#1 Eksempel A: Kartlegge behov Why: piloteringen skulle bygge på kartleggingen av behov #1 is closed, so there is no longer anything to wait for. Linked Nov 1 by erikhag1git Click to open #10solution-task-management-examples#2 Eksempel B: Skissere løsning waits for solution-task-management-examples#1 Eksempel A: Kartlegge behov Why: behovene må være kartlagt før løsningen kan skisseres #1 is closed, so there is no longer anything to wait for. Linked Nov 1 by erikhag1git Click to open #2solution-task-management-examples#3 Eksempel C: Avklare juridiske spørsmål waits for solution-task-management-examples#1 Eksempel A: Kartlegge behov Why: kartleggingen viser hvilke juridiske spørsmål som må avklares #1 is closed, so there is no longer anything to wait for. Linked Nov 1 by erikhag1git Click to open #3solution-task-management-examples#4 Eksempel D: Bygge prototype waits for solution-task-management-examples#3 Eksempel C: Avklare juridiske spørsmål Why: prototypen kan ikke behandle personopplysninger før behandlingsgrunnlaget er avklart Overlap: 9 working days (#3 ends Nov 25, #4 starts Nov 13) Linked Nov 1 by erikhag1git Click to open #4solution-task-management-examples#4 Eksempel D: Bygge prototype waits for solution-task-management-examples#2 Eksempel B: Skissere løsning Why: prototypen bygger på løsningsskissen Overlap: 1 working days (#2 ends Nov 15, #4 starts Nov 13) Linked Nov 1 by erikhag1git Click to open #4solution-task-management-examples#7 Eksempel G: Dokumentere erfaringer waits for solution-task-management-examples#2 Eksempel B: Skissere løsning Not described. Write a line under the heading Avhengigheter (Dependencies) in #7. No slack (#2 ends Nov 15, #7 starts Nov 16) Linked Nov 1 by erikhag1git Click to open #7solution-task-management-examples#18 Eksempel O: Lage presentasjon waits for solution-task-management-examples#15 Eksempel L: Intervjue fagfolk Why: presentasjonen skal vise funnene fra intervjuene Overlap: 2 working days (#15 ends Nov 20, #18 starts Nov 19) Linked Nov 2 by erikhag1git Click to open #18solution-task-management-examples#16 Eksempel M: Planlegge workshop waits for solution-task-management-examples#15 Eksempel L: Intervjue fagfolk Why: workshopen bygger på det som kom fram i intervjuene No slack (#15 ends Nov 20, #16 starts Nov 23) Linked Nov 2 by erikhag1git Click to open #16solution-task-management-examples#8 Eksempel H: Vurdere personvernkonsekvenser waits for solution-task-management-examples#3 Eksempel C: Avklare juridiske spørsmål Why: vurderingen bygger på de juridiske avklaringene Overlap: 2 working days (#3 ends Nov 25, #8 starts Nov 24) Linked Nov 1 by erikhag1git Click to open #8solution-task-management-examples#17 Eksempel N: Oppsummere intervjuene waits for solution-task-management-examples#15 Eksempel L: Intervjue fagfolk Not described. Write a line under the heading Avhengigheter (Dependencies) in #17. Slack: 5 working days (#15 ends Nov 20, #17 starts Nov 30) Linked Nov 2 by erikhag1git Click to open #17solution-task-management-examples#5 Eksempel E: Teste med brukere waits for solution-task-management-examples#4 Eksempel D: Bygge prototype Why: brukertesten trenger en prototype som virker Overlap: 9 working days (#4 ends Dec 17, #5 starts Dec 7) Linked Nov 1 by erikhag1git Click to open #5solution-task-management-examples#6 Eksempel F: Beslutte videreføring waits for solution-task-management-examples#5 Eksempel E: Teste med brukere Why: beslutningen bygger på resultatene fra brukertesten No slack (#5 ends Dec 24, #6 starts Dec 25) Linked Nov 1 by erikhag1git Click to open #6TodayArrow: waits forRed arrow: blocking task ends too lateRing: the dependency is described⛔Waits for an open taskDark: has happenedLight: dates setDashed: calculated or assumedYellow border and line: late startRed: after the due date (light: forecast)✓CompletedHatched and ✕: closed without being doneBracket: the sub-issues together (red border: one is delayed)▾ ▸Collapse and expand the sub-issuesYellow: My tasks (signed in)Generated 2026-11-15 from[EXAMPLE] Timeline. One task has no Duration and is assumed to take one week.

Where the chart is used

The timeline for a board is shown on the page Tasks and progress of the sub-project that owns the board:

Sub-projectBoard
Pilot 1Project 1
Pilot 2Project 2
Pilot 3Project 4
Pilot 4Project 3
Pilot 5Project 9
Pilot 6Project 10
Pilot 7Project 19
High-level architectureProject 5
Information architectureProject 6
SAMT-BU DocsProject 17
Task managementProject 18

The charts are all generated here, and the pages fetch them from here. See Technical documentation.

How to read the chart

  • Bar: from start to end. The colour shows the status on the board. Grey with the title struck through means the task is closed: ✓ before the title means completed, and ✕ with a hatched bar means closed without being done (in GitHub: «Close as not planned» or duplicate).
  • Dark part: what has happened, from when the task was moved to In progress until it was closed, or until today if it is still going on.
  • Light bar with border: both start and end are set (Start date and Due date) or have happened.
  • Dashed bar: at least one of the dates is calculated, see below.
  • Yellow border and yellow line under the bar: late start. The task should have started and has not. The line runs from the start date until today.
  • Red after the due date: late end. The bar is extended past the due date, and the part after the due date is red. Solid red is the time from the due date until today, when the due date has passed without the task being finished. Light red is the forecast: when the task can be finished if it starts today, or when the tasks it waits for are finished, and lasts as long as planned. The duration is Duration, otherwise the length from Start date to Due date. A delay therefore propagates: if one task is late, the tasks waiting for it can turn red before their own due date is reached.
  • Only dates someone has set give yellow and red: Start date, Due date, or a date calculated with Duration. An assumed duration never gives yellow or red.
  • Arrow: the task the arrow points to waits for the task the arrow comes from.
  • Red arrow: the task being waited for ends after the waiting task is due to start. The plan does not add up.
  • Hover over an arrow: why the task waits, slack or overlap in working days, and who linked the tasks and when. Click the arrow to see the dependency and the waiting task in the window.
  • Ring on the arrow: the dependency is described. Without a ring, the tooltip only says that the description is missing.
  • ⚠ below the chart: a task describes a dependency that is not linked in GitHub.
  • ⛔ before the title: the task is still waiting for an open task.
  • Yellow background: the task is yours, when you have selected My tasks (only when you are signed in to docs).
  • The legend below the chart shows only what is in the chart.
  • Red vertical line: today’s date.
  • Sub-issues: indented below the parent. The parent has a bracket from the first start to the last end among the sub-issues on the board, forecast included, and the progress after the number, for example «#11 · 1/3» (completed out of all sub-issues, also those on other boards). The colour of the bracket is the parent’s status on the board. The dark part is what has happened, as on the bars: the periods when at least one sub-issue was being worked on (from In progress until finished, or until today). A light gap means none of the sub-issues was being worked on then. A red border means that at least one sub-issue is delayed, and it shows also when the sub-issues are collapsed. A closed parent has a grey bracket with ✓ when completed, and a hatched bracket with ✕ when closed without being done. The status of the parent is set by hand and does not follow the sub-issues automatically. ▾ before the title collapses the sub-issues, ▸ expands them again. Arrows to and from collapsed sub-issues are hidden.

Where the dates come from

All tasks on the board are included. Start and end are found separately, in this order:

  1. What has happened. Start is the first time the task was moved to In progress (or In review) on the board. End is when the task was closed or moved to Done. GitHub records this itself.
  2. Date set: Start date and Due date on the board.
  3. Calculated from the duration: if only one of the dates exists, the other is calculated with the field Duration (working days).
  4. Calculated from the dependencies: if start is missing, the task starts the working day after the last task it waits for ends. It does not start before today, though. If it waits for nothing, it starts today.

If Duration is missing, one week (five working days) is assumed. The number of such tasks is shown below the chart. If a task goes on longer than planned, the bar is extended to today. Hover over the bar to see the dates and where they come from.

Planned and actual dates have no separate fields. What has happened is in the history in GitHub.

How a task gets the right place in the chart

  1. Set Start date and Due date on the board, or one of them and Duration. Without any of them, the task is placed after the tasks it waits for.
  2. Move the card to In progress when work begins, and close the task when it is done.
  3. If the task waits for another task: open the issue, find Relationships in the right-hand margin and choose Mark as blocked by. Choose the task being waited for. It can be in another repository.
  4. Write why the task waits under the heading Avhengigheter (dependencies) in the issue, one line per task, for example «- #35: needs legal clarification of consent». The Task form has its own field for this. If the task is in another repository, write for example samt-x/samt-bu-pilot-6#12, with samt-x/ in front, otherwise there is no link. The link itself is always the one in step 3. The text only describes it. See Conventions.

If you split a task into smaller tasks, make them sub-issues: open the parent and choose Create sub-issue or Add existing issue at the bottom of the description. The sub-issues must be on the same board to be shown under the parent in the chart.

Dependencies can also be searched for on GitHub with is:blocked, is:blocking and blocked-by:.

If the task waits for something outside GitHub, the label blocked is used instead. It gives no arrow. See Blocked in Conventions.