Tasks and progress
The tasks of pilot 7 are issues in samt-bu-pilot-7 and on the board SAMT-BU Pilot 7 – Digital dialog (Project 19). This page shows where the work stands.
Timeline All tasks on the board, with arrows showing which tasks wait for each other. What has happened is dark. Missing dates are calculated and dashed. The chart is generated from the board every hour. How to read it, and how a task gets into it: see Timeline in task management.
Oct 2026 23 24 25 26 27 28 29 30 31 Nov 2026 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 samt-bu-pilot-7#8 Team access for Pilot 7 aligned with Pilot 1-6
Done (closed: completed)
Start: Oct 26 (calculated from end and duration)
End: Oct 30 (finished)
Duration: not set, assumed 5 working days ✓ Team access for Pilot 7 aligned with Pilot 1-6 #8 samt-bu-pilot-7#8 Team access for Pilot 7 aligned with Pilot 1-6
Done (closed: completed)
Start: Oct 26 (calculated from end and duration)
End: Oct 30 (finished)
Duration: not set, assumed 5 working days samt-bu-pilot-7#1 AP1: Piloteier og team
Proposed
Start: Nov 16 (not planned, from today)
End: Nov 20 (calculated from start and duration)
Duration: not set, assumed 5 working days AP1: Piloteier og team #1 samt-bu-pilot-7#1 AP1: Piloteier og team
Proposed
Start: Nov 16 (not planned, from today)
End: Nov 20 (calculated from start and duration)
Duration: not set, assumed 5 working days samt-bu-pilot-7#2 AP2: Kartlegging og brukerbehov
Proposed
Start: Nov 16 (not planned, from today)
End: Nov 20 (calculated from start and duration)
Duration: not set, assumed 5 working days AP2: Kartlegging og brukerbehov #2 samt-bu-pilot-7#2 AP2: Kartlegging og brukerbehov
Proposed
Start: Nov 16 (not planned, from today)
End: Nov 20 (calculated from start and duration)
Duration: not set, assumed 5 working days samt-bu-pilot-7#3 AP3: Arkitektur og standardisering
Proposed
Start: Nov 16 (not planned, from today)
End: Nov 20 (calculated from start and duration)
Duration: not set, assumed 5 working days AP3: Arkitektur og standardisering #3 samt-bu-pilot-7#3 AP3: Arkitektur og standardisering
Proposed
Start: Nov 16 (not planned, from today)
End: Nov 20 (calculated from start and duration)
Duration: not set, assumed 5 working days samt-bu-pilot-7#4 AP4: Juridiske avklaringer
Proposed
Start: Nov 16 (not planned, from today)
End: Nov 20 (calculated from start and duration)
Duration: not set, assumed 5 working days AP4: Juridiske avklaringer #4 samt-bu-pilot-7#4 AP4: Juridiske avklaringer
Proposed
Start: Nov 16 (not planned, from today)
End: Nov 20 (calculated from start and duration)
Duration: not set, assumed 5 working days samt-bu-pilot-7#5 AP5: Teknisk prototype og hackathon
Proposed
Start: Nov 16 (not planned, from today)
End: Nov 20 (calculated from start and duration)
Duration: not set, assumed 5 working days AP5: Teknisk prototype og hackathon #5 samt-bu-pilot-7#5 AP5: Teknisk prototype og hackathon
Proposed
Start: Nov 16 (not planned, from today)
End: Nov 20 (calculated from start and duration)
Duration: not set, assumed 5 working days samt-bu-pilot-7#6 AP6: Felles leverandørkrav
Proposed
Start: Nov 16 (not planned, from today)
End: Nov 20 (calculated from start and duration)
Duration: not set, assumed 5 working days AP6: Felles leverandørkrav #6 samt-bu-pilot-7#6 AP6: Felles leverandørkrav
Proposed
Start: Nov 16 (not planned, from today)
End: Nov 20 (calculated from start and duration)
Duration: not set, assumed 5 working days samt-bu-pilot-7#7 Arbeidspakkene står både på «Om pilot 7» og i issuene – én master
Proposed
Start: Nov 16 (not planned, from today)
End: Nov 20 (calculated from start and duration)
Duration: not set, assumed 5 working days Arbeidspakkene står både på «Om pilot 7» og i i… #7 samt-bu-pilot-7#7 Arbeidspakkene står både på «Om pilot 7» og i issuene – én master
Proposed
Start: Nov 16 (not planned, from today)
End: Nov 20 (calculated from start and duration)
Duration: not set, assumed 5 working days