Tasks and progress

Last modified: 2026-11-02 00:12by Erik Hagen ID: 90683b51-3a3e-406f-ac45-1046600a6787 SAMT-X/samt-bu-pilot-3

The tasks of pilot 3 are issues in samt-bu-pilot-3 and on the board SAMT-BU Pilot 3 – Flytting av barn og unge i skoleåret (Project 4). This page shows where the work stands.

ViewShows
BoardAll tasks by status
By responsibleThe tasks grouped by who is responsible
Open tasksOpen tasks in a table
My tasksYour tasks (requires login)
TimelineGitHub’s own timeline, without dependencies

Timeline

All tasks on the board, with arrows showing which tasks wait for each other. What has happened is dark. Missing dates are calculated and dashed. The chart is generated from the board every hour. How to read it, and how a task gets into it: see Timeline in task management.

100 % Open the chart in a new window ↗
29Jul 20266132027Aug 2026310172431Sep 20267142128Oct 20265121926Nov 2026291623samt-bu-pilot-3#7 Opprette usikkerhetsregister for Pilot3 Done (closed: completed) Start: Jul 2 (started (In progress)) End: Jul 2 (finished)✓ Opprette usikkerhetsregister for Pilot3#7samt-bu-pilot-3#7 Opprette usikkerhetsregister for Pilot3 Done (closed: completed) Start: Jul 2 (started (In progress)) End: Jul 2 (finished)samt-bu-pilot-3#4 Oppstartsmøte august Pilot3 Done (closed: completed) Start: Jul 2 (started (In progress)) End: Aug 7 (finished)✓ Oppstartsmøte august Pilot3#4samt-bu-pilot-3#4 Oppstartsmøte august Pilot3 Done (closed: completed) Start: Jul 2 (started (In progress)) End: Aug 7 (finished)samt-bu-pilot-3#26 Møte/mini-workshop med ressurspersoner fra KS Digital Done (closed: completed) Start: Aug 10 (started (In progress)) End: Sep 15 (finished)✓ Møte/mini-workshop med ressurspersoner fra KS…#26samt-bu-pilot-3#26 Møte/mini-workshop med ressurspersoner fra KS Digital Done (closed: completed) Start: Aug 10 (started (In progress)) End: Sep 15 (finished)samt-bu-pilot-3#5 Workshop 1 - Oslo Kommune Done (closed: completed) Start: Aug 17 (started (In progress)) End: Aug 20 (finished)✓ Workshop 1 - Oslo Kommune#5samt-bu-pilot-3#5 Workshop 1 - Oslo Kommune Done (closed: completed) Start: Aug 17 (started (In progress)) End: Aug 20 (finished)samt-bu-pilot-3#27 Demo - KS Digital samtykkeløsning In progress Start: Aug 20 (started (In progress)) End: Nov 15 (still in progress, extended to today) Duration: not set, assumed 5 working daysDemo - KS Digital samtykkeløsning#27samt-bu-pilot-3#27 Demo - KS Digital samtykkeløsning In progress Start: Aug 20 (started (In progress)) End: Nov 15 (still in progress, extended to today) Duration: not set, assumed 5 working dayssamt-bu-pilot-3#28 Demo - Digdir samtykkeløsning In progress Start: Sep 15 (started (In progress)) End: Nov 15 (still in progress, extended to today) Duration: not set, assumed 5 working daysDemo - Digdir samtykkeløsning#28samt-bu-pilot-3#28 Demo - Digdir samtykkeløsning In progress Start: Sep 15 (started (In progress)) End: Nov 15 (still in progress, extended to today) Duration: not set, assumed 5 working dayssamt-bu-pilot-3#10 Gjennomfør planleggingsmøte for risikovurdering To do Start: Nov 16 (not planned, from today) End: Nov 20 (calculated from start and duration) Duration: not set, assumed 5 working daysGjennomfør planleggingsmøte for risikovurdering#10samt-bu-pilot-3#10 Gjennomfør planleggingsmøte for risikovurdering To do Start: Nov 16 (not planned, from today) End: Nov 20 (calculated from start and duration) Duration: not set, assumed 5 working dayssamt-bu-pilot-3#11 Gjennomføre første arbeidsmøte for risikovurdering (problemorientert) To do Start: Nov 16 (not planned, from today) End: Nov 20 (calculated from start and duration) Duration: not set, assumed 5 working daysGjennomføre første arbeidsmøte for risikovurder…#11samt-bu-pilot-3#11 Gjennomføre første arbeidsmøte for risikovurdering (problemorientert) To do Start: Nov 16 (not planned, from today) End: Nov 20 (calculated from start and duration) Duration: not set, assumed 5 working dayssamt-bu-pilot-3#12 Gjennomføre andre arbeidsmøte for risikovurdering (løsningsorientert) To do Start: Nov 16 (not planned, from today) End: Nov 20 (calculated from start and duration) Duration: not set, assumed 5 working daysGjennomføre andre arbeidsmøte for risikovurderi…#12samt-bu-pilot-3#12 Gjennomføre andre arbeidsmøte for risikovurdering (løsningsorientert) To do Start: Nov 16 (not planned, from today) End: Nov 20 (calculated from start and duration) Duration: not set, assumed 5 working dayssamt-bu-pilot-3#13 Gjennomfør DPIA hvis nødvendig To do Start: Nov 16 (not planned, from today) End: Nov 20 (calculated from start and duration) Duration: not set, assumed 5 working daysGjennomfør DPIA hvis nødvendig#13samt-bu-pilot-3#13 Gjennomfør DPIA hvis nødvendig To do Start: Nov 16 (not planned, from today) End: Nov 20 (calculated from start and duration) Duration: not set, assumed 5 working dayssamt-bu-pilot-3#14 Ferdigstill og arkiver risikovurdering og DPIA To do Start: Nov 16 (not planned, from today) End: Nov 20 (calculated from start and duration) Duration: not set, assumed 5 working daysFerdigstill og arkiver risikovurdering og DPIA#14samt-bu-pilot-3#14 Ferdigstill og arkiver risikovurdering og DPIA To do Start: Nov 16 (not planned, from today) End: Nov 20 (calculated from start and duration) Duration: not set, assumed 5 working dayssamt-bu-pilot-3#15 Lag kravspesifikasjon for personvern og informasjonssikkerhet To do Start: Nov 16 (not planned, from today) End: Nov 20 (calculated from start and duration) Duration: not set, assumed 5 working daysLag kravspesifikasjon for personvern og informa…#15samt-bu-pilot-3#15 Lag kravspesifikasjon for personvern og informasjonssikkerhet To do Start: Nov 16 (not planned, from today) End: Nov 20 (calculated from start and duration) Duration: not set, assumed 5 working dayssamt-bu-pilot-3#16 Planlegg fast sjekkpunkt for å fange opp endringer To do Start: Nov 16 (not planned, from today) End: Nov 20 (calculated from start and duration) Duration: not set, assumed 5 working daysPlanlegg fast sjekkpunkt for å fange opp endrin…#16samt-bu-pilot-3#16 Planlegg fast sjekkpunkt for å fange opp endringer To do Start: Nov 16 (not planned, from today) End: Nov 20 (calculated from start and duration) Duration: not set, assumed 5 working dayssamt-bu-pilot-3#17 Gjennomfør kodereview av sikkerhet og dokumentere To do Start: Nov 16 (not planned, from today) End: Nov 20 (calculated from start and duration) Duration: not set, assumed 5 working daysGjennomfør kodereview av sikkerhet og dokumente…#17samt-bu-pilot-3#17 Gjennomfør kodereview av sikkerhet og dokumentere To do Start: Nov 16 (not planned, from today) End: Nov 20 (calculated from start and duration) Duration: not set, assumed 5 working dayssamt-bu-pilot-3#18 Vurder behov for og gjennomfør eventuell pentest To do Start: Nov 16 (not planned, from today) End: Nov 20 (calculated from start and duration) Duration: not set, assumed 5 working daysVurder behov for og gjennomfør eventuell pentest#18samt-bu-pilot-3#18 Vurder behov for og gjennomfør eventuell pentest To do Start: Nov 16 (not planned, from today) End: Nov 20 (calculated from start and duration) Duration: not set, assumed 5 working dayssamt-bu-pilot-3#19 Oppdater risikovurdering og legg til nye risikoer. To do Start: Nov 16 (not planned, from today) End: Nov 20 (calculated from start and duration) Duration: not set, assumed 5 working daysOppdater risikovurdering og legg til nye risiko…#19samt-bu-pilot-3#19 Oppdater risikovurdering og legg til nye risikoer. To do Start: Nov 16 (not planned, from today) End: Nov 20 (calculated from start and duration) Duration: not set, assumed 5 working dayssamt-bu-pilot-3#20 Avklar rollefordeling for løsningen To do Start: Nov 16 (not planned, from today) End: Nov 20 (calculated from start and duration) Duration: not set, assumed 5 working daysAvklar rollefordeling for løsningen#20samt-bu-pilot-3#20 Avklar rollefordeling for løsningen To do Start: Nov 16 (not planned, from today) End: Nov 20 (calculated from start and duration) Duration: not set, assumed 5 working dayssamt-bu-pilot-3#21 Avklar behov for og inngå/oppdater databehandleravtaler To do Start: Nov 16 (not planned, from today) End: Nov 20 (calculated from start and duration) Duration: not set, assumed 5 working daysAvklar behov for og inngå/oppdater databehandle…#21samt-bu-pilot-3#21 Avklar behov for og inngå/oppdater databehandleravtaler To do Start: Nov 16 (not planned, from today) End: Nov 20 (calculated from start and duration) Duration: not set, assumed 5 working dayssamt-bu-pilot-3#22 Oppdater behandlingsprotokoll To do Start: Nov 16 (not planned, from today) End: Nov 20 (calculated from start and duration) Duration: not set, assumed 5 working daysOppdater behandlingsprotokoll#22samt-bu-pilot-3#22 Oppdater behandlingsprotokoll To do Start: Nov 16 (not planned, from today) End: Nov 20 (calculated from start and duration) Duration: not set, assumed 5 working dayssamt-bu-pilot-3#23 Lag eller oppdater personvernerklæring To do Start: Nov 16 (not planned, from today) End: Nov 20 (calculated from start and duration) Duration: not set, assumed 5 working daysLag eller oppdater personvernerklæring#23samt-bu-pilot-3#23 Lag eller oppdater personvernerklæring To do Start: Nov 16 (not planned, from today) End: Nov 20 (calculated from start and duration) Duration: not set, assumed 5 working dayssamt-bu-pilot-3#24 Lag evt. maler og veiledere (eks. til ROS/DPIA) To do Start: Nov 16 (not planned, from today) End: Nov 20 (calculated from start and duration) Duration: not set, assumed 5 working daysLag evt. maler og veiledere (eks. til ROS/DPIA)#24samt-bu-pilot-3#24 Lag evt. maler og veiledere (eks. til ROS/DPIA) To do Start: Nov 16 (not planned, from today) End: Nov 20 (calculated from start and duration) Duration: not set, assumed 5 working dayssamt-bu-pilot-3#25 Ferdigstill sluttrapport for personvern og digital sikkerhet To do Start: Nov 16 (not planned, from today) End: Nov 20 (calculated from start and duration) Duration: not set, assumed 5 working daysFerdigstill sluttrapport for personvern og digi…#25samt-bu-pilot-3#25 Ferdigstill sluttrapport for personvern og digital sikkerhet To do Start: Nov 16 (not planned, from today) End: Nov 20 (calculated from start and duration) Duration: not set, assumed 5 working dayssamt-bu-pilot-3#29 Kontakte Oslo Kommune ang. kategorisering elevmappe To do Start: Nov 16 (not planned, from today) End: Nov 20 (calculated from start and duration) Duration: not set, assumed 5 working daysKontakte Oslo Kommune ang. kategorisering elevm…#29samt-bu-pilot-3#29 Kontakte Oslo Kommune ang. kategorisering elevmappe To do Start: Nov 16 (not planned, from today) End: Nov 20 (calculated from start and duration) Duration: not set, assumed 5 working dayssamt-bu-pilot-3#30 Kontakte Nittedal Kommune ang. kategorisering elevmappe To do Start: Nov 16 (not planned, from today) End: Nov 20 (calculated from start and duration) Duration: not set, assumed 5 working daysKontakte Nittedal Kommune ang. kategorisering e…#30samt-bu-pilot-3#30 Kontakte Nittedal Kommune ang. kategorisering elevmappe To do Start: Nov 16 (not planned, from today) End: Nov 20 (calculated from start and duration) Duration: not set, assumed 5 working dayssamt-bu-pilot-3#6 Workshop 1 - Nittedal kommune To do Start: Nov 16 (not planned, from today) End: Nov 20 (calculated from start and duration) Duration: not set, assumed 5 working daysWorkshop 1 - Nittedal kommune#6samt-bu-pilot-3#6 Workshop 1 - Nittedal kommune To do Start: Nov 16 (not planned, from today) End: Nov 20 (calculated from start and duration) Duration: not set, assumed 5 working dayssamt-bu-pilot-3#8 Undersøke prosess når barnevern er involvert i flytting To do Start: Nov 16 (not planned, from today) End: Nov 20 (calculated from start and duration) Duration: not set, assumed 5 working daysUndersøke prosess når barnevern er involvert i…#8samt-bu-pilot-3#8 Undersøke prosess når barnevern er involvert i flytting To do Start: Nov 16 (not planned, from today) End: Nov 20 (calculated from start and duration) Duration: not set, assumed 5 working dayssamt-bu-pilot-3#9 Tegn planlagt brukerreise og dataflyt for ny løsning To do Start: Nov 16 (not planned, from today) End: Nov 20 (calculated from start and duration) Duration: not set, assumed 5 working daysTegn planlagt brukerreise og dataflyt for ny lø…#9samt-bu-pilot-3#9 Tegn planlagt brukerreise og dataflyt for ny løsning To do Start: Nov 16 (not planned, from today) End: Nov 20 (calculated from start and duration) Duration: not set, assumed 5 working daysTodayDark: has happenedDashed: calculated or assumed✓CompletedYellow: My tasks (signed in)Generated 2026-11-15 fromSAMT-BU Pilot 3 – Flytting av barn og unge i skoleåret. 23 tasks have no Duration and are assumed to take one week.