Tasks and progress
The tasks of pilot 2 are issues in samt-bu-pilot-2 and on the board SAMT-BU Pilot 2 – Valg av utdanningsløp (Project 2). This page shows where the work stands.
Timeline All tasks on the board, with arrows showing which tasks wait for each other. What has happened is dark. Missing dates are calculated and dashed. The chart is generated from the board every hour. How to read it, and how a task gets into it: see Timeline in task management.
May 2026 4 11 18 25 Jun 2026 1 8 15 22 29 Jul 2026 6 13 20 27 Aug 2026 3 10 17 24 31 Sep 2026 7 14 21 28 Oct 2026 5 12 19 26 Nov 2026 2 9 16 23 samt-bu-pilot-2#5 Forventningsavklaring (mål, scope, leveranser)
In progress
Start: May 6 (started (In progress))
End: May 6 (Due date)
Overdue: should have been finished May 6 Forventningsavklaring (mål, scope, leveranser) #5 samt-bu-pilot-2#5 Forventningsavklaring (mål, scope, leveranser)
In progress
Start: May 6 (started (In progress))
End: May 6 (Due date)
Overdue: should have been finished May 6 samt-bu-pilot-2#8 Novari: Kartlegge eksisterende Nå-situasjon av dokumentasjon vi har for vilbli.no
In progress
Start: May 6 (started (In progress))
End: May 29 (Due date)
Overdue: should have been finished May 29 Novari: Kartlegge eksisterende Nå-situasjon av… #8 samt-bu-pilot-2#8 Novari: Kartlegge eksisterende Nå-situasjon av dokumentasjon vi har for vilbli.no
In progress
Start: May 6 (started (In progress))
End: May 29 (Due date)
Overdue: should have been finished May 29 samt-bu-pilot-2#7 Lage rammer for en nå-situasjon workshop
To do
Start: May 6 (started (In progress))
End: Jun 12 (Due date)
Overdue: should have been finished Jun 12 Lage rammer for en nå-situasjon workshop #7 samt-bu-pilot-2#7 Lage rammer for en nå-situasjon workshop
To do
Start: May 6 (started (In progress))
End: Jun 12 (Due date)
Overdue: should have been finished Jun 12 samt-bu-pilot-2#6 Etablere metodikk og arbeidsform
Done (closed: completed)
Start: May 6 (started (In progress))
End: Aug 7 (finished) ✓ Etablere metodikk og arbeidsform #6 samt-bu-pilot-2#6 Etablere metodikk og arbeidsform
Done (closed: completed)
Start: May 6 (started (In progress))
End: Aug 7 (finished) samt-bu-pilot-2#19 HK-dir: Kartlegge eksisterende Nå-situasjon av dokumentasjon vi har for utdanning.no
In review
Start: May 8 (started (In progress))
End: May 29 (Due date)
Overdue: should have been finished May 29 HK-dir: Kartlegge eksisterende Nå-situasjon av… #19 samt-bu-pilot-2#19 HK-dir: Kartlegge eksisterende Nå-situasjon av dokumentasjon vi har for utdanning.no
In review
Start: May 8 (started (In progress))
End: May 29 (Due date)
Overdue: should have been finished May 29 samt-bu-pilot-2#10 Starte arbeidet med en interessent / aktør oversikt
In progress
Start: Jun 5 (started (In progress))
End: Jun 5 (Due date)
Overdue: should have been finished May 29 Starte arbeidet med en interessent / aktør over… #10 samt-bu-pilot-2#10 Starte arbeidet med en interessent / aktør oversikt
In progress
Start: Jun 5 (started (In progress))
End: Jun 5 (Due date)
Overdue: should have been finished May 29 samt-bu-pilot-2#11 Utarbeide et forslag for fremtids løsning (med eksempler/scenarier)
In progress
Start: Aug 7 (started (In progress))
End: Aug 14 (Due date)
Overdue: should have been finished Aug 14 Utarbeide et forslag for fremtids løsning (med… #11 samt-bu-pilot-2#11 Utarbeide et forslag for fremtids løsning (med eksempler/scenarier)
In progress
Start: Aug 7 (started (In progress))
End: Aug 14 (Due date)
Overdue: should have been finished Aug 14 samt-bu-pilot-2#17 Forslag til fremtidig eierskap og forvaltning
In progress
Start: Aug 7 (started (In progress))
End: Nov 15 (still in progress, extended to today)
Duration: not set, assumed 5 working days Forslag til fremtidig eierskap og forvaltning #17 samt-bu-pilot-2#17 Forslag til fremtidig eierskap og forvaltning
In progress
Start: Aug 7 (started (In progress))
End: Nov 15 (still in progress, extended to today)
Duration: not set, assumed 5 working days samt-bu-pilot-2#12 Erfaringsrapport fra Pilot 2: Valg av utdanningsløp
To do
Start: Nov 16 (not planned, from today)
End: Nov 20 (calculated from start and duration)
Duration: not set, assumed 5 working days Erfaringsrapport fra Pilot 2: Valg av utdanning… #12 samt-bu-pilot-2#12 Erfaringsrapport fra Pilot 2: Valg av utdanningsløp
To do
Start: Nov 16 (not planned, from today)
End: Nov 20 (calculated from start and duration)
Duration: not set, assumed 5 working days samt-bu-pilot-2#13 Forslag til gevinster for Pilot 2: Valg av utdanningsløp
To do
Start: Nov 16 (not planned, from today)
End: Nov 20 (calculated from start and duration)
Duration: not set, assumed 5 working days Forslag til gevinster for Pilot 2: Valg av utda… #13 samt-bu-pilot-2#13 Forslag til gevinster for Pilot 2: Valg av utdanningsløp
To do
Start: Nov 16 (not planned, from today)
End: Nov 20 (calculated from start and duration)
Duration: not set, assumed 5 working days samt-bu-pilot-2#14 Forslag til arbeid rundt juridiske avklaringer
To do
Start: Nov 16 (not planned, from today)
End: Nov 20 (calculated from start and duration)
Duration: not set, assumed 5 working days Forslag til arbeid rundt juridiske avklaringer #14 samt-bu-pilot-2#14 Forslag til arbeid rundt juridiske avklaringer
To do
Start: Nov 16 (not planned, from today)
End: Nov 20 (calculated from start and duration)
Duration: not set, assumed 5 working days samt-bu-pilot-2#15 Forslag til informasjonsmodel
To do
Start: Nov 16 (not planned, from today)
End: Nov 20 (calculated from start and duration)
Duration: not set, assumed 5 working days Forslag til informasjonsmodel #15 samt-bu-pilot-2#15 Forslag til informasjonsmodel
To do
Start: Nov 16 (not planned, from today)
End: Nov 20 (calculated from start and duration)
Duration: not set, assumed 5 working days samt-bu-pilot-2#16 Forslag til arkitektur
To do
Start: Nov 16 (not planned, from today)
End: Nov 20 (calculated from start and duration)
Duration: not set, assumed 5 working days Forslag til arkitektur #16 samt-bu-pilot-2#16 Forslag til arkitektur
To do
Start: Nov 16 (not planned, from today)
End: Nov 20 (calculated from start and duration)
Duration: not set, assumed 5 working days samt-bu-pilot-2#18 Forslag til samarbeidsavtale
To do
Start: Nov 16 (not planned, from today)
End: Nov 20 (calculated from start and duration)
Duration: not set, assumed 5 working days Forslag til samarbeidsavtale #18 samt-bu-pilot-2#18 Forslag til samarbeidsavtale
To do
Start: Nov 16 (not planned, from today)
End: Nov 20 (calculated from start and duration)
Duration: not set, assumed 5 working days